InstallationTerminals Of Ecu
TERMINALS OF ECU
1. CHECK MAIN BODY ECU (MULTIPLEX NETWORK BODY ECU)
(a) Disconnect the 1D and 1F driver side junction block connectors.
(b) Measure the voltage and resistance according to the value(s) in the table
below.
HINT:
Measure the values on the wire harness side with the connectors ...
Removal
REMOVAL
PROCEDURE
1. REMOVE FRONT DOOR SCUFF PLATE LH (for Double Cab)
2. REMOVE FRONT DOOR SCUFF PLATE LH (for Access Cab)
3. REMOVE COWL SIDE TRIM BOARD LH
4. REMOVE CENTER INSTRUMENT CLUSTER CENTER FINISH PANEL SUB-ASSEMBLY
5. REMOVE INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY
...
Operation Check
OPERATION CHECK
CHECK LANE DEPARTURE ALERT MAIN SWITCH
(a) Check the lane departure alert main switch (steering pad switch assembly)
on/off operation.
(1) Turn the ignition switch to ON.
(2) Confirm that the lane departure alert indicator (green) in the combination
meter assembly illuminates ...