Replacement
ComponentsFog Light Relay
Inspection
INSPECTION
PROCEDURE
1. INSPECT FOG LIGHT RELAY
(a) Check the resistance.
(1) Using an ohmmeter, measure the resistance between the terminals.
Standard:
Tester Connection
Specified Condition
3-5
10 kΩ or higher
...
Installation
INSTALLATION
PROCEDURE
1. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY
(a) Install the transmission control cable assembly from outside the vehicle
body and attach the 3 claws of the cable retainer.
(b) Install the 2 nuts.
Torque:
5.5 N·m {56 kgf·cm, 49 in·lbf}
(c) Connect the transmissi ...
Daytime Running Light Relay
Inspection
INSPECTION
PROCEDURE
1. INSPECT NO. 1 DAY TIME RUNNING LIGHT RELAY
(a) Check the resistance.
(1) Measure the resistance according to the value(s) in the table below.
Standard:
Tester Connection
Condition
Specified ...