INSTALLATION

PROCEDURE

1. INSTALL GENERATOR ASSEMBLY

(a) Install the generator bracket to the generator assembly with the bolt.

Torque:

20 N·m {204 kgf·cm, 15 ft·lbf}

(b) Install the generator assembly with the 2 bolts.

Torque:

43 N·m {438 kgf·cm, 32 ft·lbf}

(c) Connect the generator bracket to the cylinder block sub-assembly with the bolt.

Torque:

20 N·m {204 kgf·cm, 15 ft·lbf}

(d) Engage the clamp and connect the engine wire to the generator bracket.

(e) Connect the engine wire to the generator assembly with the 2 bolts.

Torque:

8.0 N·m {82 kgf·cm, 71 in·lbf}

(f) Connect the engine wire to the terminal B with the nut.

Torque:

9.8 N·m {100 kgf·cm, 87 in·lbf}

(g) Install the terminal cap.

(h) Connect the connector to the generator assembly .

(i) Install the wire harness clamp bracket with the bolt.

Torque:

8.0 N·m {82 kgf·cm, 71 in·lbf}

(j) Engage the clamp and install the engine wire to the wire harness clamp bracket.

2. INSTALL NO. 1 SURGE TANK STAY

Click here 3. INSTALL NO. 2 IDLER PULLEY SUB-ASSEMBLY

3. INSTALL NO. 2 IDLER PULLEY SUB-ASSEMBLY

(a) Install the No. 2 idler pulley sub-assembly with the bolt.

Torque:

43 N·m {438 kgf·cm, 32 ft·lbf}

4. INSTALL V-BANK COVER

Click here 5. INSTALL BATTERY TRAY

5. INSTALL BATTERY TRAY

6. INSTALL BATTERY

7. INSTALL BATTERY CLAMP SUB-ASSEMBLY

(a) Install the battery clamp sub-assembly and tighten the nut.

Torque:

5.4 N·m {55 kgf·cm, 48 in·lbf}

8. CONNECT CABLE TO POSITIVE BATTERY TERMINAL

Torque:

5.4 N·m {55 kgf·cm, 48 in·lbf}

9. CONNECT CABLE TO NEGATIVE TERMINAL

Torque:

5.4 N·m {55 kgf·cm, 48 in·lbf}

NOTICE:

When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

Click here Reassembly

Inspection
INSPECTION PROCEDURE 1. INSPECT GENERATOR BRUSH HOLDER ASSEMBLY (a) Using a vernier caliper, measure the brush length. Text in Illustration *a Len ...

Reassembly
REASSEMBLY PROCEDURE 1. INSTALL GENERATOR DRIVE END FRAME BEARING (a) Using SST and a press, press in a new generator drive end frame bearing. SST: 09950-60010 09951-00470 SST: ...

Other materials:

Removal
REMOVAL PROCEDURE 1. PRECAUTION NOTICE: After turning the ignition switch off, waiting time may be required before disconnecting the cable from the negative (-) battery terminal. Therefore, make sure to read the disconnecting the cable from the negative (-) battery terminal notices before p ...

Reassembly
REASSEMBLY PROCEDURE 1. INSTALL SHIFT SOLENOID VALVE SLT (a) Install the shift solenoid valve SLT and straight pin to the transmission valve body assembly. 2. INSTALL SHIFT SOLENOID VALVE SL2 (a) Install the shift solenoid valv ...

Clearance Warning Buzzer Circuit
DESCRIPTION This circuit consists of the No. 1 clearance warning buzzer and clearance warning ECU assembly. An ECU-excited type buzzer is used. The battery voltage supplied through the buzzer is grounded inside the clearance warning ECU assembly using a pulsed digital pattern, producing sound ...

© 2011-2018 Copyright www.ttguide.net