Back-up Power Source Circuit
Parts LocationNetwork Gateway Ecu
Components
COMPONENTS
ILLUSTRATION
Installation
INSTALLATION
PROCEDURE
1. INSTALL NETWORK GATEWAY ECU
(a) Install the network gateway ECU with the bolt.
Torque:
3.0 N·m {31 kgf·cm, 27 in·lbf}
(b) Connect the connector.
2. INSTALL LOWER INSTRUMENT PANEL ASSEMBLY
(See page )
R ...
Turn signal lever
Right turn
Left turn
Move and hold the lever partway to
signal a lane change.
The right hand signal will flash until you release the lever.
Move and hold the lever partway
to signal a lane change.
The left hand signal will flash until you release the lever.
■Turn signals can be ...
Low Pitched Horn
Components
COMPONENTS
ILLUSTRATION
Inspection
INSPECTION
PROCEDURE
1. INSPECT LOW PITCHED HORN ASSEMBLY
(a) Check the operation.
(1) Apply battery voltage to the terminal 1 and body ground, and check
that the low pitched horn assembly sounds.
Text in Illustration
...