Air conditioning systemPurge Valve
Components
COMPONENTS
ILLUSTRATION
Inspection
INSPECTION
PROCEDURE
1. INSPECT PURGE VSV
(a) Measure the resistance according to the value(s) in the table below.
Text in Illustration
*a
Component without harness connected
(Purge VSV ...
Installation
INSTALLATION
PROCEDURE
1. INSTALL INSTRUMENT PANEL SUB-ASSEMBLY
(a) Engage the 5 guides to install the instrument panel sub-assembly.
(b) Engage the clamps and connect the connectors.
(c) Install the nut <G>.
(d) Install the 8 bolts <A>.
(e) Install the 2 bolts <B> or 2 bo ...
Operation Check
OPERATION CHECK
1. CHECK POWER DOOR LOCK OPERATION
NOTICE:
The operation check below is based on the non-customized initial condition of
the vehicle.
(a) Check basic functions.
(1) Check that all doors lock when the lock side of the door control switch is
pressed.
(2) Check that all doors ...