DESCRIPTION
Refer to Slip Indicator Light Remains ON (See page ).
WIRING DIAGRAM
Refer to Slip Indicator Light Remains ON (See page ).
CAUTION / NOTICE / HINT
NOTICE:
PROCEDURE
1. |
CHECK CAN COMMUNICATION SYSTEM |
NG |
GO TO CAN COMMUNICATION SYSTEM (HOW TO PROCEED WITH TROUBLESHOOTING) |
|
2. |
PERFORM ACTIVE TEST USING TECHSTREAM (SLIP INDICATOR LIGHT) |
(a) Connect the Techstream to the DLC3.
(b) Turn the ignition switch to ON.
(c) Turn the Techstream on.
(d) Enter the following menus: Chassis / ABS/VSC/TRAC / Active Test.
(e) According to the display on the Techstream, perform the Active Test.
ABS/VSC/TRAC
Tester Display |
Test Part |
Control Range |
Diagnostic Note |
---|---|---|---|
Slip Indicator Light |
Slip indicator light |
Indicator light OFF/ON |
Observe the combination meter. [Vehicle condition] Vehicle stopped |
(f) When performing the slip Warning Light Active Test, check slip indicator light in the Data List.
ABS/VSC/TRAC
Tester Display |
Measurement Item/Range |
Normal Condition |
Diagnostic Note |
---|---|---|---|
Slip Indicator Light |
Slip indicator light/ ON or OFF |
ON: Indicator light on OFF: Indicator light off |
- |
Result |
Proceed to |
---|---|
Slip indicator light in the Data List does not change using the Active Test |
A |
Slip indicator light in the Data List turns ON/OFF using the Active Test |
B |
A |
REPLACE MASTER CYLINDER SOLENOID |
|
3. |
INSPECT COMBINATION METER ASSEMBLY |
(a) Turn the ignition switch off.
(b) Perform Active Test of the combination meter assembly using the Techstream.
(c) Check the combination meter assembly.
OK:
The slip warning light turns on or off in accordance with the Techstream.
OK |
REPLACE MASTER CYLINDER SOLENOID |
NG |
GO TO METER / GAUGE SYSTEM |
List of storage features
Glove box
Overhead console (Access Cab and
Double Cab models)
Bottle holders
Auxiliary boxes
Front console box (separated type
front seat only)
Cup holders
CAUTION
■Items that should not be left in the storage spaces
Do not leave glasses, lighters or spray cans in the stora ...
Installation
INSTALLATION
PROCEDURE
1. INSTALL GENERATOR ASSEMBLY
(a) Install the generator bracket to the generator assembly with the bolt.
Torque:
20 N·m {204 kgf·cm, 15 ft·lbf}
(b) Install the generator assembly with the 2 bolts.
Torque:
43 N·m {438 kgf·cm, 32 ft·lbf}
(c) Connect the generato ...
Installation
INSTALLATION
PROCEDURE
1. INSTALL REAR SEATBACK HINGE SUB-ASSEMBLY
(a) Install the rear seatback hinge sub-assembly with the 2 bolts.
Torque:
30 N·m {306 kgf·cm, 22 ft·lbf}
2. INSTALL REAR SEATBACK ASSEMBLY
(a) Install the rear seatback assembly with the 2 bolts.
Torque:
37 N·m {377 k ...