Installation
ComponentsBack-up Light Switch
Components
COMPONENTS
ILLUSTRATION
Inspection
INSPECTION
PROCEDURE
1. INSPECT BACK-UP LIGHT SWITCH ASSEMBLY
(a) Measure the resistance according to the value(s) in the table below.
Text in Illustration
*a
Pushed
...
Hydraulic Test
HYDRAULIC TEST
1. PERFORM HYDRAULIC TEST
(a) Measure the line pressure.
CAUTION:
The line pressure test should always be performed with at least 2 people. One
person should observe the condition of the wheels and wheel chocks while the other
is performing the test.
NOTICE:
Perform ...
Neutral Position Switch Circuit
DESCRIPTION
The ECM uses the neutral position switch installed to the manual transmission
assembly to detect when the transmission is in the neutral position.
WIRING DIAGRAM
PROCEDURE
1.
READ VALUE USING TECHSTREAM (NEUTRAL SWITCH)
(a) Connect the Techstream ...