Toyota Tacoma manuals

Toyota Tacoma (2015-2018) Service Manual: Installation

INSTALLATION

PROCEDURE

1. INSTALL VANE PUMP ASSEMBLY

(a) Install the vane pump assembly with the 2 bolts.

Torque:

21 N·m {214 kgf·cm, 15 ft·lbf}

(b) Connect the ground wire with the bolt.

Torque:

8.5 N·m {87 kgf·cm, 75 in·lbf}

2. CONNECT PRESSURE FEED TUBE ASSEMBLY

(a) Install a new gasket to the pressure feed tube assembly.

(b) Connect the pressure feed tube assembly with the union bolt.

Torque:

50 N·m {510 kgf·cm, 37 ft·lbf}

(c) Connect the oil pressure switch connector.

NOTICE:

Make sure that no oil adheres to the connector.

3. CONNECT NO. 1 OIL RESERVOIR TO PUMP HOSE

(a) Connect the No. 1 oil reservoir to pump hose and slide the clip to secure it.

4. INSTALL FRONT FENDER APRON UPPER SEAL RH

5. INSTALL FAN AND GENERATOR V BELT 5. INSTALL FAN AND GENERATOR V BELT

5. INSTALL FAN AND GENERATOR V BELT

6. ADD POWER STEERING FLUID

6. ADD POWER STEERING FLUID

7. BLEED POWER STEERING FLUID

8. INSPECT FOR POWER STEERING FLUID LEAK

8. INSPECT FOR POWER STEERING FLUID LEAK

9. INSTALL NO. 1 ENGINE UNDER COVER SUB-ASSEMBLY

Torque:

30 N·m {306 kgf·cm, 22 ft·lbf}

10. INSTALL NO. 2 ENGINE UNDER COVER SUB-ASSEMBLY (w/ Off Road Package)

Torque:

30 N·m {306 kgf·cm, 22 ft·lbf}

Inspection
INSPECTION PROCEDURE 1. INSPECT OIL CLEARANCE (a) Using a micrometer and caliper gauge, measure the oil seal clearance. Text in Illustration *1 Pu ...

Vane Pump(for 2tr-fe)
...

Other materials:

Camper information
This information has been prepared in accordance with regulation issued by the National Highway Traffic Safety Administration of the U.S. Department of Transportation. It provides the purchasers and/or prospective purchasers of Toyota vehicles with information on truck-camper loading. Your Toy ...

High Beam Headlight Circuit
DESCRIPTION The main body ECU (multiplex network body ECU) controls the high beam headlights. WIRING DIAGRAM CAUTION / NOTICE / HINT NOTICE: Inspect the fuses for circuits related to this system before performing the following inspection procedure. If the main body ECU (multip ...

Inspection
INSPECTION PROCEDURE 1. INSPECT TIE ROD END SUB-ASSEMBLY (a) Flip the ball joint stud back and forth 5 times as shown in the illustration before installing the nut. (b) Using a torque wrench, turn the nut continuously at a rate of 2 to 4 seconds per turn and check the torque reading on the ...

© 2011-2026 Copyright www.ttguide.net